The IDEAL Assistive Technology (AT) SmartDrive® Development Processes
Quality Assurance Plan
Last
updated on October 16, 2006
I. Objective
II. Required Entities
III. Process
IV. Application Testing
V. Quality Assurance Processes
A. Budget
B. Project Plan
C. Communication Plan
D. Issues-Log
E. Functional Requirements
F. Technical Specifications
G. User Documentation
H. Training Materials
I. Alpha and Beta testing Scripts
J. Final Deliverable Review Plan
K. Post-Implementation Review
The
objective of Access Tomorrow’s assistive technology (AT) software U3 migration Quality Assurance (QA) plan
is to:
-
Ensure that all
steps of the AT U3 migration process are monitored for quality.
-
Ensure the use of
proper user acceptance testing protocols for each AT migrated.
-
Determine sign-off
procedures for milestone achievements
-
Test teams, one for
each of the following disability groups:
-
Advisory Board
comprised of technology experts from each of the above disability groups in
addition to other experts.
QA
will be maintained through Alpha testing, correction/enhancements, Beta-testing,
final correction/enhancements and final reviews.
For
application evaluation:
-
Alpha and Beta
testers will use scripts that were designed to test the success of the U3
migration
-
All testing will be
recorded and the results thoroughly documented.
-
Technical staff will
make U3 programming changes as necessary.
The
Quality Assurance process will include the following:
Budget will be reviewed by advisory committee for:
The
PI, development team and the advisory committee will review the project plan:
-
to ensure milestone
dates are on target,
-
for any changes in
scope, and
-
for possible trouble
spots.
The
communication plan will be monitored by the advisory committee to ensure that
communications among project staff is sufficient and effective.
The
project team will review the log document on a daily basis (PI weekly review) to
ensure that:
-
target dates for
resolution are being met;
-
high-priority
actions are being resolved first; and,
-
the project is not
put in jeopardy for any reason.
PI,
members of the advisory committee, project team members and user groups will
ensure that all functions of the source AT port successfully to the U3 platform.
PI
sign-off required.
The
development team will document the U3 migration process. The
PI, members of the advisory committee,
development team and user groups will review the U3 migration process.
PI
sign-off required.
Users, the PI, members of the advisory committee, and project team members will
test (users only) and review the user documentation.
PI
sign-off required.
PI,
members of the advisory committee, and project team members review the training
materials.
PI
sign-off required.
Project team to develop testing scripts based upon the specifications by
disability.
PI
sign-off required.
PI,
members of the advisory committee, and project team members review final
deliverables to insure that they ported to U3 successfully and passed all user
tests.
PI
sign-off required.
A
post implementation review will take place among the PI, members of the advisory
committee, and project team members to document what was done right and wrong
and what needs to be improved.
PI
sign-off required.
|